Pricing the Risk: Bankable PPAs to Narrow the ASEAN Energy Transition Investment Gap

Author : Ambiyah Abdullah 25 September 2026

ASEAN aims to achieve 30% and 45% shares of renewable energy (RE) in total primary energy supply (TPES) and installed capacity by 2030, respectively, yet remains around 16 percentage points short of meeting the 2030 RE share target in TPES, indicating the need for urgent action. The key bottleneck to the slow deployment of RE and other energy transition projects in ASEAN is not the availability of technology or capital, but rather the bankability of these projects, fragmented regulations, and other factors stemming from the high risk perceived by private investors. Thus, it is crucial to meet the conditions for bankability from the private investor's perspective. One critical criterion set by the private investor in assessing the bankability of a project is whether risk allocation is fairly distributed between the project company and the contractor, including off-takers, particularly to ensure expected revenue with a limited margin associated with an energy transition project over the longer payback period. In this context, the cost of an energy transition project in ASEAN includes all costs required to cover risks arising before and after implementation. For ASEAN and other developing countries, off-taker and currency risks are viewed as two critical risks for private investors.

In addition to derisking mechanisms, the choice of contractual agreement type (which indicates the financial project structure) provides complementary mitigation measures to address off-taker risks and enhance the bankability of energy transition projects in the region. A Power Purchase Agreement (PPA) offers long-term certainty to private investors by setting an electricity price between the electricity generator and consumers for the duration of the project.  Compared with the engineering, procurement, and construction (EPC) contract agreement type, the PPA- based independent power producer (IPP) offers the project owner an advantage by avoiding high upfront capital costs and shifting construction and operational risks to the private project developer. The next critical question is how to design a PPA to unlock the bankability of energy transition projects in ASEAN. The bankable PPA is required to ensure the certainty of expected revenue for private investors and to establish clear risk allocation and institutional arrangements to cover debt financing during the agreed project period, typically 15 to 25 years. The expected revenue is closely linked to the pricing mechanism set under the PPA, which is central to it. The choice of pricing mechanisms is aimed either at revenue certainty (fixed, take-or-pay, and market) or at market efficiency (CfD, auction, and charges) and needs to be coordinated between regulators and private investors.

Moreover, the pricing mechanism set under the PPA affects the second critical factor of bankability: the risk allocation between the parties to the agreement. Most ASEAN Member States (AMS) applied fixed or flat price mechanisms aiming to ensure revenue certainty to boost the deployment of clean energy technologies, in particular for the previous energy transition projects, such as Vietnam's fixed FIT to boost solar deployment in Vietnam during 2017-2021, the previously applied Philippine FIT under the Renewable Energy Act 2008, and Indonesia's previously applied IPP scheme.

Fixed FIT schemes are well-suited to early-stage RE deployment by shifting most of the risks to the government and state-owned utility companies, but impose a heavy burden on the fiscal budget. As a result, two new pricing mechanisms under the PPA in several AMS have now moved to competitive auction-based pricing and bilateral negotiated pricing. For example, the Philippines’ Green Energy Auction (GEA-5), which set a Green Energy Auction Reserve price of around PHP 11.00/kWh and utilized the Renewable Energy Payment Agreement (REPA), the new PLN Indonesia procurement ceiling, and Vietnam’s Direct Power Purchase Agreement (DPPA). Although the auction ceiling price aims to open competition among energy developers, setting it at the right level is crucial. These examples show a shift from fixed-price schemes, although regulatory structures and mechanisms still differ considerably across AMS.

Similar to the ceiling price, the bilateral negotiated pricing mechanism offers a complementary pricing scheme that might be suitable for data centers and assigned industrial customers to purchase electricity directly from specified private energy developers, such as Malaysia’s Corporate Renewable Energy Supply Scheme (CRESS) and the Philippines’ RCOA contestable customer contract and Contract for Difference (CfD). Although the bilateral negotiated price scheme is complementary to the previously stated pricing scheme, it also entails two key risks: high transaction costs and limited standardisation and transparency in price mechanisms.

Although the central purpose of the pricing mechanisms under the PPA scheme is to reallocate risk and enhance the bankability of energy projects, the administrative task of designing the PPA contract could increase the project's cost of capital. Clear preparatory work and PPA contract drafting can reduce potential capital costs. As market conditions and the electricity system in AMS vary, regional cooperation could instead pursue a standardized PPA framework that includes common core terms (risk allocation, termination, and others), along with tailored parameters that reflect each AMS’ market conditions. This would also facilitate the cross-border transmission project. Last but not least, setting the right PPA risk pricing and allocation is the key to unlocking private capital mobilized to narrow the ASEAN energy transition investment gap. 

Cover image credit: Magnific